04-11-2020
Transportes Angel Velasco is mainly in charge of transporting one of the Covid modules, a module measuring 15 x 4.90 x 4 meters and weighing 10 tons.

To carry it out, one of our drivers plus the pilot car used a 6x4 tractor plus a low-loader with three axles.

We collaborate and we will continue to do so until we all overcome the pandemic.

The new equipment at Parc Sanitari Pere Virgili will have a constructed area of ​​approximately 4,000 square meters and will be completed before the end of the year.
It will have a maximum capacity of 108 beds in intensive care units. The parameterized design and its execution with a high content of off-site manufacturing allows the design and construction process to be carried out in just four months. Each UCI floor has a capacity for between 24 and 36 beds, occupying an area of ​​972 square meters.

The modules transported to achieve this rapid assembly were made with 6x2 tractors and lowered gondola, with modules of 15 x 4.90 x 4.00 and 15 tons.

Transports delivered without incident and on time by our drivers, Gomis, Venancio, Reverte, Alex, Jose Maria, and Juan Carlos.

Thank you for your work team